10 Hudson Yards

Last updated

10 Hudson Yards
10 Hudson Yard from 9 Av & 30 St 2016 Dec jeh.jpg
Seen in 2016
10 Hudson Yards
Alternative namesSouth Tower
General information
StatusCompleted
Type Office
Location501 West 30th Street
New York, NY 10001 [1]
Coordinates 40°45′09″N74°00′04″W / 40.7525°N 74.0010°W / 40.7525; -74.0010
GroundbreakingDecember 4, 2012
Construction startedAugust 2013
CompletedMay 31, 2016
Management The Related Companies
Oxford Properties
Height
Roof878 feet (268 m)
Top floor704 feet (215 m)
Technical details
Floor count52
Floor area1,700,698 square feet (158,000.0 m2)
Lifts/elevators27
Design and construction
Architect(s) Kohn Pedersen Fox (architect & master planner)
Main contractor Tutor Perini Building
Website
Official website
References
[2] [3]
10 Hudson Yards
Map of buildings and structures at Hudson Yards. Zoom the map and click on points for more details.
'"`UNIQ--templatestyles-0000000B-QINU`"''"`UNIQ--templatestyles-0000000C-QINU`"'

10 Hudson Yards, also known as the South Tower, is an office building that was completed in 2016 [4] in Manhattan's West Side. Located near Hell's Kitchen, Chelsea and the Penn Station area, the building is a part of the Hudson Yards urban renewal project, a plan to redevelop the Metropolitan Transportation Authority's West Side Yard. Coach New York is the anchor tenant. During planning, the tower was known as Tower C. [5]

Contents

History

Construction

Hudson Yards, conceived through a large master plan by Kohn Pedersen Fox, is expected to consist of 16 skyscrapers containing more than 12.7 million square feet (1,180,000 m2) of new office, residential, and retail space. Among its components will be 6 million square feet (560,000 m2) of commercial office space, a 750,000-square-foot (70,000 m2) retail center with two levels of restaurants, cafes, markets and bars, a hotel, a cultural space, about 5,000 residences, a 750-seat school, and 14 acres (5.7 ha) of public open space. 10 Hudson Yards, the first building on the site, is expected to help draw visitors to the area. [6]

March 2016 10 Hudson Yards 31 March 2016.png
March 2016

Groundbreaking for 10 Hudson Yards occurred on December 4, 2012, [5] [4] with a provisional completion date of 2016. [7] Foundation work continued through the first half of 2013 and the superstructure work began on the tower in August 2013. [8] During excavation work, 70,000 cubic yards (54,000 m3) of soil was removed and 11,000 cubic yards (8,400 m3) of concrete was poured. [9] The contract to construct the tower was awarded to a subsidiary of Tutor Perini in March 2013. [10] The tower is the first tower in the Hudson Yards complex to have been completed, because it is the only Hudson Yards tower not on the artificial platform over the West Side Yards. [11]

As of March 2014, 10 Hudson Yards had risen more than 100 feet (30 m). [12] As of February 2015, 10 Hudson Yards was 27 stories tall. [13] As of April 2015, thirty-two of the tower's 52 floors had been completed. [14] As of November 2015, 10 Hudson Yards had topped out. [15] The tower was opened on May 31, 2016, with the first 300 Coach, Inc. employees moving into the building. [16] As of November 2022, 10 Hudson Yards was the 49th-tallest building in the United States. [17]

The southern facade of 10 Hudson Yards cantilevers over the 30th Street spur of the High Line, and one of the building's entrances is to be located on the High Line. [9] The architectural firm who designed 10 Hudson Yards was Kohn Pedersen Fox. [6] [9] [18] Thornton Tomasetti was the structural engineer; Jaros, Baum & Bolles performed the MEP engineering; and Langan served as lead civil engineer. [17] In January 2019, the developers unveiled a 30 feet (9.1 m) long sculpture by American artist Jonathan Borofsky for the west lobby. [19]

Occupancy

The first tenants were signed in April 2013. [20] The building is anchored by Tapestry, Inc.'s global headquarters, which covers 737,774 square feet (68,541 m2) on floors 9 to 24 within the tower. [9] Coach's space includes a 15-story atrium, double height conference rooms overlooking the High Line, a private cafeteria, and a large terrace with views of the Hudson River. [21] Coach was the first tenant to move into the new building on May 31, 2016. In September 2017, Coach subleased 148,000 square feet (13,700 m2) of space to The Guardian Life Insurance Company of America. [22]

Building Entrance At New York, USA 2017 228.jpg
Building Entrance

In total, the building was designed to accommodate over 7,000 employees. [21] Additional occupants include L'Oreal USA, [9] Boston Consulting Group, SAP, and Intersection [9] occupying 402,000 square feet (37,300 m2), 193,295 square feet (17,957.7 m2) and 115,000 square feet (10,700 m2), and 67,000 square feet (6,200 m2) respectively. [23] VaynerMedia occupies the building's 25th floor. [24] [25]

There will also be retail space at street level adjacent to the retail building immediately to the north of 10 Hudson Yards. That building will be designed by Elkus Manfredi Architects. [26] Fairway, a locally based grocer, was expected to build a store in the lower floors of the building, occupying 45,875 square feet (4,262 m2). [9] [27] Additionally, Spanish chef José Andrés will operate a 35,000 square feet (3,300 m2) food hall named Mercado Little Spain which will contain a wine bar, a cocktail bar, and 15 kiosks serving different kinds of tapas. [28] An outpost of fast casual salad restaurant Sweetgreen opened in August 2018 in the base of the tower. [29]

Ownership

10 Hudson Yards was initially owned by the master developers of the Hudson Yards project, Related Companies and Oxford Properties, in partnership with the Kuwait Investment Authority. Various sections of the tower were sold to tenants as office condos, with Coach purchasing their space for $750 million prior to construction. [30] In August 2016, Coach sold their stake in the tower to Allianz for $420 million. The deal gave Allianz 44% ownership and valued the building at $2.15 billion. [30] [31] In May 2018, the State Teachers Retirement System of Ohio purchased roughly 20% of the tower for $432 million at a similar valuation. [32] [33]

See also

Related Research Articles

<span class="mw-page-title-main">Riverside South, Manhattan</span> Building complex in New York City

Riverside South is an urban development project in the Lincoln Square neighborhood of the Upper West Side of Manhattan, New York City. It was originated by six civic associations – The Municipal Art Society, Natural Resources Defense Council, New Yorkers for Parks, Regional Plan Association, Riverside Park Fund, and Westpride – in partnership with real estate developer Donald Trump. The largely residential complex, located on the site of a former New York Central Railroad yard, includes Freedom Place and Riverside Center. The $3 billion project is on 57 acres (23 ha) of land along the Hudson River between 59th Street and 72nd Street.

<span class="mw-page-title-main">1 New York Plaza</span> Office skyscraper in Manhattan, New York

1 New York Plaza is an office building in the Financial District of Manhattan in New York City, at the intersection of South and Whitehall Streets near South Ferry. The building, measuring 640 feet (200 m) tall with 50 floors, is the southernmost skyscraper in Lower Manhattan. It was designed by William Lescaze & Assocs. and Kahn & Jacobs, and developed by Sol Atlas and John P. McGrath.

<span class="mw-page-title-main">Hudson Yards, Manhattan</span> Neighborhood in New York City

Hudson Yards is a neighborhood on the West Side of Midtown Manhattan in New York City, bounded roughly by 30th Street in the south, 41st Street in the north, the West Side Highway in the west, and Eighth Avenue in the east. The area is the site of a large-scale redevelopment program that is being planned, funded, and constructed under a set of agreements among the State of New York, City of New York, and Metropolitan Transportation Authority (MTA), with the aim of expanding the Midtown Manhattan business district westward to the Hudson River. The program includes a major rezoning of the Far West Side, an extension of the New York City Subway's 7 and <7>​ trains to a new subway station at 34th Street and 11th Avenue, a renovation and expansion of the Javits Center, and a financing plan to fund the various components. The various components are being planned by New York City Department of City Planning and New York City Economic Development Corporation.

<span class="mw-page-title-main">Truist Center</span> Truist headquarters and 47-story skyscraper in downtown Charlotte, North Carolina

The Truist Center is a 47-story, 659 feet (201 m) skyscraper in Uptown Charlotte, North Carolina. The city's third tallest building, it is located along North Tryon Street. It was opened on November 14, 2002, and was the city's second tallest building, and was known as the "Hearst Tower" until 2019. The structure is composed of a 32-story tower resting atop a 15-floor podium. During Bank of America's occupancy in the building located on the podium was a three-story trading facility designed by Skidmore, Owings & Merrill and operated by Bank of America. The trading facility included a 6,000-square-foot (560 m2), two-story trading floor. Now the former trading floor is part of Truist's 100,000 square feet (9,300 m2) technology innovation center. The building is currently the headquarters of Truist Financial, which purchased the building in March 2020.

<span class="mw-page-title-main">One South at The Plaza</span> Office / Retail in South Tryon Street

One South at The Plaza is a 503 feet (153 m), 40-story skyscraper in Charlotte, North Carolina. It is the 7th tallest in the city. It contains 891,000 square feet (82,777 m2) of rentable area of which 75,000 sq ft (7,000 m2) of retail space, and the rest office space. On the ground floor is the Overstreet Mall, which connects to neighboring buildings via skybridges; located below-grade is the parking garage with space for 456 vehicles and leases a nearby five-level garage, providing 730 additional parking spaces.

Manhattan West is a 7-million-square-foot (650,000 m2) mixed-use development by Brookfield Properties, built as part of the Hudson Yards Redevelopment. The project spans 8 acres and features four office towers, one boutique hotel, one residential building, 225,000 square feet (20,900 m2) of retail space and a 2.5-acre public plaza. The project was built on a platform over Penn Station storage tracks along Ninth Avenue between 32nd and 33rd Streets.

<span class="mw-page-title-main">Asia Square</span> Twin-tower mixed-use development at Marina Bay, Singapore

Asia Square is a retail and office building located along Marina View at Marina Bay in Singapore. It is located in Marina Bay, Singapore's new business and financial precinct. It comprises 2,000,000 square feet (190,000 m2) of office space, over 30 entertainment and dining premises, as well as the largest gym in the Central Business District.

<span class="mw-page-title-main">Telus Sky</span> Skyscraper in Calgary, Alberta, Canada

Telus Sky, is a 60-storey, 222.3 m (729 ft) mixed-use skyscraper in downtown Calgary, Alberta, Canada. At completion in 2019, the structure building became the third-tallest building in Calgary behind Brookfield Place East and The Bow. As of July 2020, Telus Sky is the 18th tallest building in Canada, though several buildings in Toronto exceeding its height are under construction including The One.

<span class="mw-page-title-main">30 Hudson Yards</span> Skyscraper in Manhattan, New York

30 Hudson Yards is a supertall skyscraper in Midtown Manhattan's West Side, New York City. It is positioned near Hell's Kitchen, Chelsea, and NY Penn Station. As of November 2022, the building is the sixth-tallest in New York City and the eighth-tallest in the United States. It is a key structure in the Hudson Yards Redevelopment Project, which aims to revitalize the West Side Yard of the Metropolitan Transportation Authority.

15 Hudson Yards is a residential skyscraper on Manhattan's West Side, completed in 2019. Located in Chelsea near Hell's Kitchen Penn Station area, the building is a part of the Hudson Yards project, a plan to redevelop the Metropolitan Transportation Authority's West Side Yards.

<span class="mw-page-title-main">35 Hudson Yards</span> Residential skyscraper in Manhattan, New York

35 Hudson Yards is a mixed-use skyscraper in Manhattan's West Side composed of apartment units and a hotel. Located near Hell's Kitchen, Chelsea, and the Penn Station area, the building is a part of the Hudson Yards project, a plan to redevelop the Metropolitan Transportation Authority's West Side Yards. As of November 2022, it was the 28th-tallest building in the United States.

<span class="mw-page-title-main">50 Hudson Yards</span> Office skyscraper in Manhattan, New York

50 Hudson Yards is a 58-story, 981-foot (299 m)-tall building that was developed as part of the Hudson Yards Redevelopment Project in Hudson Yards, Manhattan, New York City. The building is located to the north of 30 Hudson Yards, and on the east side of the Hudson Park and Boulevard, adjacent to 55 Hudson Yards. The building opened on October 19, 2022.

<span class="mw-page-title-main">55 Hudson Yards</span> Office skyscraper in Manhattan, New York

55 Hudson Yards is a skyscraper in Hudson Yards, Manhattan, New York City, just outside the Hudson Yards Redevelopment Project. It and 50 Hudson Yards will add a combined 4 million square feet (370,000 m2) of space to the Hudson Yards project, even though the two buildings are located outside the redevelopment site itself.

<span class="mw-page-title-main">The Shed (arts center)</span> Cultural center in New York City

The Shed is a cultural center in Hudson Yards, Manhattan, New York City. Opened on April 5, 2019, the Shed commissions, produces, and presents a wide range of activities in performing arts, visual arts, and pop culture.

<span class="mw-page-title-main">Millennium Tower (Boston)</span> Skyscraper in Boston, Massachusetts, US

Millennium Tower is a 60-story, 684-foot-tall (208 m) residential skyscraper in Boston, Massachusetts, United States. Construction began in 2013 at the site of the former flagship store for Filene's in Downtown Crossing and was completed in 2016. As of 2022, it is the fifth tallest building in Boston. The building contains 442 condominiums, a Roche Bros. grocery store and Class A office space. Limited occupancy by residents began in July 2016.

520 West 41st Street was a proposed 106-story supertall skyscraper in Hudson Yards, Manhattan, New York City, near Midtown Manhattan. The building would have surpassed all other skyscrapers on the island by floor-count. Upon completion, it would either have been the fifth or sixth tallest building in New York City.

<span class="mw-page-title-main">The Spiral (New York City)</span> Skyscraper in Manhattan, New York

The Spiral, also known as 66 Hudson Boulevard, is a 66-floor, 1,031-foot (314 m) skyscraper with 2.85 million square feet (265,000 m2), on 34th Street between Hudson Boulevard and Tenth Avenue in Hudson Yards, Manhattan, New York City. It was developed by Tishman Speyer, constructed by Turner Construction, and opened in 2023.

One Manhattan West is a 67-story office skyscraper at 395 Ninth Avenue in the Manhattan West development on the West Side of Manhattan in New York City, United States. Designed by Skidmore, Owings & Merrill (SOM), it was completed in 2019 and is the second tower to be completed in the development after 3 Manhattan West. The tower is rectangular in plan, with a curtain wall that contains insulated glazing, as well as a reinforced-concrete mechanical core. Because One Manhattan West partially overhangs a set of railroad tracks, the mechanical core carries most of the building's structural loads.

<span class="mw-page-title-main">Hudson Yards (development)</span> Development project in Manhattan, New York

Hudson Yards is a 28-acre (11 ha) real estate development in the Hudson Yards neighborhood in Manhattan, New York City, between the Chelsea and Hell's Kitchen neighborhoods. It is located on the waterfront of the Hudson River. Upon completion, 13 of the 16 planned structures on the West Side of Midtown South would sit on a platform built over the West Side Yard, a storage yard for Long Island Rail Road trains. The first of its two phases, opened in 2019, comprises a public green space and eight structures that contain residences, a hotel, office buildings, a mall, and a cultural facility. The second phase, on which construction had not started as of 2023, will include residential space, an office building, and a school.

<span class="mw-page-title-main">The Shops & Restaurants at Hudson Yards</span> Shopping mall in New York City

The Shops & Restaurants at Hudson Yards is an upscale indoor shopping mall in New York City, located at 20 Hudson Yards, at 33rd Street and Tenth Avenue, within the Hudson Yards complex in Midtown Manhattan. It was built with 1 million square feet (93,000 m2) of space, including 750,000 square feet (70,000 m2) in retail. Of this, 445,000 square feet (41,300 m2) was converted to office space in 2023.

References

  1. "High-rise office building evacuated in Manhattan after fire breaks out on 23rd floor". ABC7 New York. WABC-TV. November 17, 2017. Archived from the original on February 15, 2020. Retrieved February 15, 2020.
  2. "10 Hudson Yards". CTBUH Skyscraper Center .
  3. "Emporis building ID 1195442". Emporis . Archived from the original on March 6, 2016.
  4. 1 2 Peltz, Jennifer (December 4, 2012). "Hudson Yards Tower Construction Begins With Groundbreaking Ceremony (IMAGES)". Huff Post. Archived from the original on December 8, 2015. Retrieved May 12, 2014.
  5. 1 2 "Hudson Yards Set to Alter Skyline, Transform Neighborhood". Chelsea Now. February 6, 2013. Archived from the original on July 24, 2014. Retrieved June 2, 2014.
  6. 1 2 Volpe, Joseph (May 7, 2014). "New York's next big neighborhood is its smartest". Engadget . Archived from the original on May 8, 2014. Retrieved May 9, 2014.
  7. Slatin, Peter (June 4, 2014). "Veteran Team Designs Tower". The Wall Street Journal . Archived from the original on December 22, 2015. Retrieved June 4, 2014.
  8. "A New Neighborhood, from the Ground Up". Chelsea Now. February 6, 2013. Archived from the original on February 13, 2018. Retrieved May 16, 2017.
  9. 1 2 3 4 5 6 7 "10 Hudson Yards Fact Sheet" (PDF). Archived (PDF) from the original on October 6, 2014. Retrieved May 13, 2014.
  10. "Tutor Perini awarded contract for Hudson Yards South Tower - New York Business Journal". Bizjournals.com. March 27, 2013. Archived from the original on December 16, 2013. Retrieved May 12, 2014.
  11. "Hudson Yards Platform Soon to be Underway, Sparking Eastern Rail Yard". Chelsea Now. February 26, 2014. Archived from the original on June 25, 2014. Retrieved June 2, 2014.
  12. Levitt, David (March 19, 2014). "New York's Hudson Yards Starts Next Phase as Deck Begins". Bloomberg. Archived from the original on November 28, 2016. Retrieved June 4, 2014.
  13. "Progress Report: Hudson Yards". Chelsea Now. Archived from the original on February 8, 2015. Retrieved February 21, 2015.
  14. Dailey, Jessica (June 10, 2015). "Hudson Yards Construction Rolls On As Retail Center Rises". Curbed NY. Archived from the original on September 23, 2015. Retrieved June 20, 2015.
  15. Rosenberg, Zoe (October 7, 2015). "The First Hudson Yards Tower Now Stands At Full Height". Curbed NY. Retrieved January 14, 2016.
  16. Kirby, Jen (May 31, 2016). "Take a Peek Into 10 Hudson Yards, the New Neighborhood's First Shiny Skyscraper to Open for Business". Daily Intelligencer. Archived from the original on June 1, 2016. Retrieved June 1, 2016.
  17. 1 2 "10 Hudson Yards - The Skyscraper Center". www.skyscrapercenter.com. Retrieved November 3, 2022.
  18. Rosenberg, Zoe (May 27, 2014). "Contested Hudson Yards Tower Gets Another New Look". Curbed NY. Archived from the original on February 10, 2015. Retrieved June 4, 2014.
  19. Morris, Sebastian (January 31, 2019). "Related And Oxford Unveil Commissioned Art Installations At Hudson Yards". New York Yimby. Archived from the original on February 1, 2019. Retrieved January 31, 2019.
  20. Bagli, Charles V. (April 10, 2013). "First Hudson Yards Tower Signs Three Major Tenants". City Room. Archived from the original on September 15, 2017. Retrieved May 16, 2017.
  21. 1 2 "HUDSON YARDS WELCOMES ITS FIRST EMPLOYEES AND OFFICIALLY OPENS ITS DOORS". Related Companies. May 31, 2016. Archived from the original on September 16, 2018. Retrieved March 3, 2019.
  22. "Here's how much Guardian is paying Coach for Hudson Yards sublease". The Real Deal New York. September 15, 2017. Archived from the original on September 15, 2017. Retrieved September 15, 2017.
  23. "MarketWatch.com". MarketWatch.com. April 10, 2013. Archived from the original on December 3, 2013. Retrieved May 12, 2014.
  24. Gancsos, Ben. "VaynerMedia Offices – Manhattan". Office Snapshots. Office Snapshots LLC. Archived from the original on January 24, 2019. Retrieved January 23, 2019.
  25. Levitt, David M (November 13, 2015). "Hudson Yards Owners Seek Buyer for 40% Interest in First Tower". Bloomberg.com. Archived from the original on March 17, 2017. Retrieved April 9, 2016.
  26. Voien, Guelda (January 1, 2014). "Hudson Yards retail gets underway, with construction and marketing set to begin at Far West Side site this month". The Real Deal. Archived from the original on May 23, 2014. Retrieved June 4, 2014.
  27. "HudsonYards | News and press :: Fairway Market to be Anchor Food Market at Hudson Yards". Hudsonyardsnewyork.com. Archived from the original on November 30, 2013. Retrieved May 12, 2014.
  28. "HUDSON YARDS ANNOUNCES LATEST ADDITIONS AND DETAILS ON FORTHCOMING DINING COLLECTION OPENING MARCH 15, 2019". Related Companies. February 6, 2019. Archived from the original on July 24, 2022. Retrieved March 3, 2019.
  29. "HUDSON YARDS ANNOUNCES FAST-CASUAL ADDITIONS TO DINING COLLECTION". Related Companies. December 4, 2018. Archived from the original on July 24, 2022. Retrieved March 3, 2019.
  30. 1 2 "Allianz buys 44% stake in 10 Hudson Yards". The Real Deal. August 2, 2016. Archived from the original on December 27, 2018. Retrieved December 27, 2018.
  31. Cullen, Terence (August 2, 2016). "Allianz Bags Coach's Share of 10 Hudson Yards for $420M". Commercial Observer. Retrieved August 6, 2022.
  32. "Ohio teachers' pension fund makes $432M investment in Hudson Yards". The Real Deal. May 18, 2018. Archived from the original on May 3, 2019. Retrieved December 27, 2018.
  33. Barhanovich, Jody (May 22, 2018). "Ohio STRS invests $432m in Manhattan office building - News". Institutional Real Estate, Inc. Retrieved August 6, 2022.

Further reading