Pentagon Renovation Program

Last updated

A composite aerial view showing the renovations to the Pentagon. PENREN.jpg
A composite aerial view showing the renovations to the Pentagon.

The Pentagon Renovation Program (PENREN) was a long-term project by the United States Department of Defense to perform a complete slab-to-slab renovation of the Pentagon in Arlington, Virginia. The program began in the 1990s, and was completed in June 2011. [1] [2]

Contents

The full-scale renovation became necessary because by the mid-1990s, the Pentagon had never undergone a major renovation and building systems had deteriorated beyond repair, requiring complete replacement. Asbestos throughout the building made almost any building work complex and disruptive. [3]

The Defense Authorization Act of 1991 transferred control of the Pentagon Reservation from the General Services Administration to the Department of Defense, and established the Pentagon Reservation Maintenance Revolving Fund, designed to fund Pentagon renovations. This move enabled the Secretary of Defense to determine rental rates for Pentagon tenants to help fund the renovation. [3]

Projects

Information technology

The basic information system infrastructure in the Pentagon was installed long before the advent of personal computers, fax machines, video teleconferencing, and digital telephone service, and had evolved without a design plan. In 1943, when the Pentagon was built, there was one telephone for every three employees. Over the following years, new information technology capabilities had emerged and new systems had been laid on top of the old. Over time, this merging of technology had become unmanageable and not easily upgraded. As requirements emerged, facilities and systems were added with little or no regard to existing capabilities or long-term requirements. The individual military departments and agencies engineered and installed equipment and cables to meet their immediate specific needs.

The renovated Pentagon contains over 1,700 miles (2,700 km) of cabling, more than 100,000 voice, data, and video drops, 50,000 data faceplates, and 16 consolidated server rooms, down from 70 server rooms before. [4]

Metro entrance facility

Pentagon bus facility during grand opening ceremonies on December 18, 2001. Pentagon Bus Facility.jpg
Pentagon bus facility during grand opening ceremonies on December 18, 2001.

When the Washington Metro's Pentagon station originally opened, access to the Pentagon from the station was gained through a direct underground entrance. An outdoor bus station also existed at the station's street entrance.

As part of the renovation, vehicular traffic was moved further away from the building itself, and the direct entrance from the Metro station was eliminated in order to enhance security. This involved constructing a new dual-level bus station beyond the original bus station, and constructing a new Metro entrance facility. The new entrance facility is accessed from street level, with a covered path leading from the bus station past the Metro station entrance to the Pentagon itself.

In addition, the opening of the bus facility marked the return of bus traffic to the Pentagon, after having been moved to the Pentagon City station due to security changes made following the attack on the Pentagon on September 11, 2001. [5]

The Navy Build-Out project is located in the basement of Wedge 4 and consists of approximately 30,000 square feet (2,800 m2) of occupiable space. Demolition and abatement of this space was completed in November 2001. The build-out contract was awarded in September 2001 and construction began in early November 2001. The contractor designed and constructed office space, conference/training rooms, and supporting spaces including mechanical rooms, telephone closets, electrical closets, bathrooms, equipment rooms, etc. to house the Navy. [6]

In order to fulfill the new structural requirements of the renovation design over 200 helical screwed piles were installed through the existing slab on grade to support a new floor slab. The original completion date was set as March 2003, with tenant move in scheduled for April 2003. The project was completed in June 2003. [7]

Pentagon Athletic Center

The original facility, the Pentagon Officers Athletic Club was located east of the Pentagon on the opposite side of the abandoned railroad track. It had never undergone a physical renovation. PAC management made it a point to keep the facility updated with modern equipment. However, the projected increase in usage would soon exceed the amount of space available. The replacement PAC is located on the north side of the Pentagon next to the Remote Delivery Facility and new helipad and is more than 50% larger, and accommodates 8,000 members per day, compared to the 2,000 members per day supported by the POAC. The additional space increased the facility's capacity to bring in more workout equipment, allow for more varied exercise areas and rooms, and help to reduce crowded conditions during peak hours. [8]

Pentagon Library and Conference Center

The Pentagon Library and Conference Center project, also known as PLC2, transformed the former Pentagon Athletic Center into the new home for the Army library, 16 conference rooms operated by the Department of Defense Concessions Committee, several offices under the Pentagon Force Protection Agency, and also a cafe for catering purposes. Design elements include a two-story grand hall entrance, terrazzo flooring, and large skylights to provide natural light.

Due to the former Pentagon Athletic Center's being completely underground, in creating the new facility, PENREN had to completely demolish the original structure, leaving only the surrounding walls and roof intact. [9]

Pentagon Memorial

The Pentagon Memorial is located on the southwest side of the Pentagon that was struck on September 11, 2001, and is designed so that the nation may remember and reflect on the events that occurred on that date. The Memorial is free and open to the public seven days a week. Groups and individuals are welcome in the Memorial each day but guided tours are not offered; the Memorial is meant to be experienced on a more personal level. The Pentagon Memorial is located at 1 Rotary Road on the Pentagon Reservation in Arlington. [10] Although most other such memorials are located either near the main entrance or the north side of Arlington National Cemetery, the Memorial is within walking distance of the new United States Air Force Memorial and share parking with it.

Similar to other PENREN construction projects, the Memorial Project is also focusing on sustainability. The project's sustainable efforts include: site development through reclaimed land development and its proximity to mass transportation; and in high efficiency through low impact mechanical, electrical, and plumbing (fountain) systems. Additionally, the Memorial project teams are tracking erosion and sediment control, stormwater management, and light pollution reduction. The Leadership in Energy and Environmental Design (LEED) credits achieved from this project will contribute to the overall Pentagon Reservation certification. [11]

Phoenix Project

Construction work to repair the damaged portion of the Pentagon as part of the Phoenix Project. Pentagon Phoenix Project Construction.jpg
Construction work to repair the damaged portion of the Pentagon as part of the Phoenix Project.
Project Phoenix Countdown to September 11, 2002 | Work on Wedge 1 - Pentagon Project Phoenix Let's Roll.jpg
Project Phoenix Countdown to September 11, 2002 | Work on Wedge 1 – Pentagon
From the third floor looking northwest at repair preparation, October 2001 Project Phoenix Repair Prep Oct2001.jpg
From the third floor looking northwest at repair preparation, October 2001
Project Phoenix repair work nearing completion Project Phoenix April 2002.jpg
Project Phoenix repair work nearing completion

The Phoenix Project was the name given to the project to repair the damage to the Pentagon caused when American Airlines Flight 77 crashed into the building during the September 11, 2001 attacks. The project's goal was to reoccupy the outermost ring of the rebuilt section by September 11, 2002. This goal was bettered by nearly a month, with tenants moving back in on August 15, 2002.

The project entailed the complete demolition and reconstruction of the C, D, and E Rings in the area of the boundary between the recently renovated Wedge 1 and the unrenovated Wedge 2. Wedge 1 space would be fully rebuilt, while only the building shell would be rebuilt for Wedge 2. A full build-out for the Wedge 2 space would be completed at a later time.

The phrase "Let's roll", as spoken by Todd Beamer on United Airlines Flight 93, was adopted as the project's slogan, and displayed prominently on the building's exterior during the reconstruction work. A clock counting down the time until 9:37 AM on September 11, 2002, was located on site as well. [12]

Remote Delivery Facility

The Remote Delivery Facility (RDF) is a new 250,000-square-foot (23,000 m2) shipping and receiving facility adjoining the Pentagon. The RDF significantly improves the physical security of the Pentagon by providing a secure consolidated location for receiving and screening thousands of items shipped to the building each day.

The Remote Delivery facility contains 38 loading docks, and receives an average of 250 trucks per day. The roof is landscaped to create a park-like atmosphere, and is the first major project to utilize a design-build delivery system. [13] The Pentagon helipad was relocated from the site of the Pentagon Memorial to the roof of the RDF.

Roads, grounds, and security

Initiated as a direct result of the terrorist attack, the Pentagon Roads, Grounds, and Security projects will enhance Pentagon perimeter security. With a combined total value of $35 million, these initiatives will increase standoff distance between the Pentagon and public roadways. These projects were completed October 2004. [14]

Two roads, grounds, and security projects are the Remote Delivery Facility Secure Access Lane along Route 27 and the Pentagon Secure Bypass Lane which involves the rerouting of Route 110 through the Pentagon North lot.

Pentagon Secure Bypass – scope of work:

RDF Secure Access Lane – scope of work:

Swing space

To keep the Pentagon operational at all times during renovation, one-fifth of the building's 25,000 occupants must be relocated to swing space, temporary office space in and around the Pentagon. The vacated "wedge" of the Pentagon is then sealed off for demolition and abatement. Over 1,000,000 square feet (93,000 m2) of external swing space was built-out in nearby Rosslyn and Crystal City. Over 45 floors of office space had to be connected to the Pentagon's voice and data communications systems. [7]

Wedge 1

Wedge 1 was the first above-ground section of the Pentagon to undergo renovation. Demolition of the existing structure and hazardous material abatement began in 1998, and the first move-in of tenants occurred in February 2001. The last tenants moved in on February 6, 2003.

The renovation of Wedge 1 involved the renovation of one million square feet of space. This involved the removal of 83 million pounds of debris (70% of this was able to be recycled), and 28 million pounds of hazardous material. The renovation also saw the installation of eight new passenger elevators, new blast-resistant windows, escalators traversing all five floors, skylights, a new HVAC system, a new communications infrastructure, and a new open-plan office layout. [15] [16]

Wedges 2–5

Wedges 2–5 is a phased design/build renovation of 4,000,000 square feet (370,000 m2) of space in the Pentagon. The project brings all remaining un-renovated areas of the building into compliance with modern building, life safety, ADA and fire codes. Work includes removal of all hazardous materials, replacement of all building systems, addition of new elevators and escalators to improve vertical circulation, and installation of new security and telecommunications systems. Renovated spaces will be modern, efficient, and flexible. The project, underway since September 2001, is on an accelerated schedule for completion in December 2010, four years sooner than originally planned.

Sustainable design measures have been integrated into the design. The Wedges 2–5 project is enrolled in the Leadership in Energy and Environmental Design (LEED) Existing Buildings Pilot Program, and is working to achieve a gold rating. Force protection initiatives prompted by the September 11, 2001 terrorist attack have been successfully incorporated into the design. These include increased blast resistance, improved fire protection/life safety, and inclusion of chemical, biological and radiological (CBR) protection.

Key project challenges include integration of changing requirements (primarily telecommunications and force protection upgrades), tenant requirements gathering, and coordination of project turnover/tenant relocations. The September 11, 2001 terrorist attack caused the Renovation Program to reassess and upgrade project design criteria in many areas. Identification and implementation of the new criteria has been extremely challenging because design and construction had to proceed while studies were in development in order to meet the overall accelerated program schedule. Tenant requirements gathering has historically been a challenge for the Renovation Program and continues to be a challenge for Wedges 2–5, particularly for nontypical tenant spaces. Project turnover and tenant relocation to newly completed space is a complex effort. It must be carefully orchestrated to ensure a smooth transition for tenant missions and timely release of new areas for renovation. [17]

Related Research Articles

<span class="mw-page-title-main">World Trade Center site</span> Grounds of the World Trade Center in New York City

The World Trade Center site, often referred to as "Ground Zero" or "the Pile" immediately after the September 11 attacks, is a 14.6-acre (5.9 ha) area in Lower Manhattan in New York City. The site is bounded by Vesey Street to the north, the West Side Highway to the west, Liberty Street to the south, and Church Street to the east. The Port Authority of New York and New Jersey (PANYNJ) owns the site's land. The original World Trade Center complex stood on the site until it was destroyed in the September 11 attacks.

<span class="mw-page-title-main">Canadian Museum of Nature</span> Natural history museum in Ontario, Canada

The Canadian Museum of Nature is a national natural history museum based in Canada's National Capital Region. The museum's exhibitions and public programs are housed in the Victoria Memorial Museum Building, a 18,910-square-metre structure (203,500 sq ft) in Ottawa, Ontario. The museum's administrative offices and scientific centres are housed at a separate location, the Natural Heritage Campus, in Gatineau, Quebec.

<span class="mw-page-title-main">Pentagon station</span> Washington Metro station

Pentagon station is a split platform station on the Washington Metro located adjacent to The Pentagon in Arlington, Virginia. The station was opened on July 1, 1977, and is operated by the Washington Metropolitan Area Transit Authority. Providing service for both the Blue and Yellow Lines, the station is where the two lines diverge and thus acts as a transfer point. Northbound, both lines rise above ground, with the Blue Line serving the Arlington Cemetery station, and the Yellow Line crossing the Potomac River into the District of Columbia.

<span class="mw-page-title-main">Martin Luther King Jr. Memorial Library</span>

The Martin Luther King Jr. Memorial Library (MLKML) is the central facility of the District of Columbia Public Library (DCPL), it was constructed and named in honor of the American civil rights leader Dr. Martin Luther King Jr. It is located in the 901 G St. NW in Downtown Washington, D.C., with its main entrance between 9th and 10th St. in the opposite corner of Gallery Place station, and the Smithsonian American Art Museum. The library is located in and around the Chinatown, Mount Vernon Square, and Penn Quarter neighborhoods.

Berlin High School is a public high school located in Berlin, Connecticut, United States.

<span class="mw-page-title-main">Maverick Stadium</span>

Maverick Stadium is a 12,500-seat multi-purpose stadium on the western edge of University of Texas at Arlington campus.

The Joe Craft Center, opened in January 2007, is a basketball practice facility and athletics office building attached to Memorial Coliseum on the "Avenue of Champions" at the University of Kentucky in Lexington, Kentucky.

<span class="mw-page-title-main">Greater Columbus Convention Center</span> Convention center in Columbus, Ohio

The Greater Columbus Convention Center (GCCC) is a convention center located in Downtown Columbus, Ohio, United States, along the east side of North High Street.

Founded in 1989, Diversified Project Management is a New England-based owners’ representative consulting company headquartered in Newton, Massachusetts. With additional offices in Hartford, Connecticut, and Stamford, Connecticut, Diversified Project Management specializes in programming, project management, construction administration, FF&E coordination and move-planning services for corporate, education, health care, manufacturing and biotechnology construction, renovation and relocation projects.

<span class="mw-page-title-main">The Summit at Danbury</span> Corporate Offices, Conference & Banquet Center in Danbury, CT

The Summit at Danbury, formerly known as the Matrix Corporate Center and before that as the Union Carbide Corporate Center, is an architecturally unique building in Danbury, Connecticut. It was constructed in 1982 as the headquarters of the Union Carbide chemical company, it is known for its unusual style and floorplan layout. The complex was designed by the late famous architect Kevin Roche who also designed other famous corporate headquarters.

<span class="mw-page-title-main">Glenn & Viola Walters Cultural Arts Center</span> Arts center in Hillsboro, Oregon, US

The Glenn & Viola Walters Cultural Arts Center is a multi-use arts and performance venue in downtown Hillsboro, Oregon, United States. Opened in 2004, it is housed in a red-colored stone building completed in 1949 as a Lutheran church. Hillsboro, a city on the west side of Portland, owns the three-level facility and operates it through their Parks and Recreation Department.

<span class="mw-page-title-main">The Pentagon</span> Headquarters of the US Department of Defense in Arlington, Virginia

The Pentagon is the headquarters building of the United States Department of Defense, in Arlington County, Virginia, across the Potomac River from Washington, D.C. It was constructed on an accelerated schedule during World War II. As a symbol of the U.S. military, the phrase The Pentagon is often used as a metonym for the Department of Defense and its leadership.

<span class="mw-page-title-main">Harry S Truman Building</span> US State Department HQ in Washington, D.C.

The Harry S Truman Building is the headquarters of the United States Department of State. It is located in Washington, D.C., and houses the office of the United States secretary of state.

<span class="mw-page-title-main">One Washington Park</span> Skyscraper

One Washington Park is a high rise office building located on Harriet Tubman Square at 1 Washington Street in Newark, New Jersey. Among the tallest buildings in the city, it is best known as the home of Rutgers Business School, Amazon's Audible.com, and Newark Venture Partners.

<span class="mw-page-title-main">U.S. Army Information Technology Agency</span> Military unit

The United States Army Information Technology Agency (ITA) is one of the administrative service organizations aligned under the Office of the Administrative Assistant to the Secretary of the Army (OAA). OAA has three fundamental functions. The primary mission of the organization is to provide direct support to the Secretary of the Army and other Army political appointees. The second mission is to provide administrative support to the Headquarters, Department of the Army (HQDA). The third mission is to provide base operations support to a diverse group of Army and Department of Defense (DoD) customers. OAA is organized into four major divisions: the U.S. Army Resources and Programs Agency (RPA), the U.S. Army Headquarters Services (AHS), the U.S. Army Information Technology Agency (ITA), and the U.S. Army Center of Military History (CMH). These divisions support OAA primarily in areas of IT, logistics, training, and human resources support.

<span class="mw-page-title-main">Terminals of Los Angeles International Airport</span> Nine passenger terminals with 133 gates

The Terminals of Los Angeles International Airport have more than 150 gates in nine passenger terminals arranged in the shape of the letter U or a horseshoe. Passengers can move between terminals via various shuttle buses and inter-terminal pedestrian connections. As of 2023, the airport is in the midst of a major reconstruction program, after which passengers will be able to make connections between all terminals on foot without having to exit and reenter airport security.

<span class="mw-page-title-main">Georgetown Car Barn</span> Historic streetcar terminal in Washington, D.C.

The Georgetown Car Barn, historically known as the Capital Traction Company Union Station, is a building in the Georgetown neighborhood of Washington, D.C., in the United States. Designed by the architect Waddy Butler Wood, it was built between 1895 and 1897 by the Capital Traction Company as a union terminal for several Washington and Virginia streetcar lines. The adjacent Exorcist steps, later named after their appearance in William Friedkin's 1973 horror film The Exorcist, were built during the initial construction to connect M Street with Prospect Street.

<span class="mw-page-title-main">Moynihan Train Hall</span> Expansion of New York Penn Station (opened 2021)

Moynihan Train Hall is an expansion of Pennsylvania Station, the main intercity and commuter rail station in New York City, into the city's former main post office building, the James A. Farley Building. Located between Eighth Avenue, Ninth Avenue, 31st Street, and 33rd Street in Midtown Manhattan, the annex provides new access to most of Penn Station's platforms for Amtrak and Long Island Rail Road passengers, serving 17 of the station's 21 tracks. The hall is named after Daniel Patrick Moynihan, the U.S. senator who had originally championed the plan. The building's Beaux-Arts exterior resembles that of the original Penn Station; both buildings were designed by the architectural firm of McKim, Mead & White.

References

  1. Vogel, Steve (22 June 2011). "New Pentagon Is A Paragon". Washington Post . p. 1.
  2. "Pentagon Renovation Program Management". Parsons Corporation. Archived from the original on 2 August 2009.
  3. 1 2 "The Pentagon Renovation Program". United States Department of Defense. Archived from the original on 25 August 2009. Retrieved 3 May 2010.
  4. "Pentagon Renovation Program". 14 February 2008. Archived from the original on 14 February 2008. Retrieved 16 October 2019.
  5. "Pentagon Renovation Program". 9 January 2008. Archived from the original on 9 January 2008. Retrieved 16 October 2019.
  6. "Pentagon Renovation Program". 9 January 2008. Archived from the original on 9 January 2008. Retrieved 16 October 2019.
  7. 1 2 "Pentagon Renovation Program". 8 January 2008. Archived from the original on 8 January 2008. Retrieved 16 October 2019.
  8. "Pentagon Renovation Program". 16 December 2007. Archived from the original on 16 December 2007. Retrieved 16 October 2019.
  9. "PENREN Completes PLC2" (PDF). 29 September 2007. Archived from the original (PDF) on 29 September 2007. Retrieved 16 October 2019.
  10. "Washington Headquarters Services". Archived from the original on 17 January 2009. Retrieved 19 April 2009.
  11. "Sustainabledesign". Archived from the original on 29 July 2009. Retrieved 19 April 2009.
  12. "Pentagon Renovation Program". 9 February 2008. Archived from the original on 9 February 2008. Retrieved 16 October 2019.
  13. "Pentagon Renovation Program". 9 January 2008. Archived from the original on 9 January 2008. Retrieved 16 October 2019.
  14. Archived May 10, 2008, at the Wayback Machine
  15. "Pentagon Renovation Program". 9 January 2008. Archived from the original on 9 January 2008. Retrieved 16 October 2019.
  16. "Pentagon Renovation Program". 9 February 2008. Archived from the original on 9 February 2008. Retrieved 16 October 2019.
  17. "Pentagon Renovation Program". Renovation.pentagon.mil. 11 September 2001. Retrieved 16 July 2009.

PD-icon.svg This article incorporates public domain material from websites or documents of the United States Government .