EastLink (Melbourne)

Last updated

EastLink

New EastLink Logo.png
Busy Eastlink (27438452052).jpg
EastLink in May 2016
EastLink (Melbourne)
Australia Victoria metropolitan Melbourne location map.svg
Red pog.svg
North end
Red pog.svg
South end
Coordinates
General information
Type Freeway
Location Melbourne
Length39 km (24 mi)
Opened29 June 2008
Maintained by ConnectEast
Route number(s) AUS Alphanumeric Route M3 toll.svg M3 (2008–present)
Major junctions
North endAUS Alphanumeric Route M3.svg Eastern Freeway
Donvale, Melbourne
 
South endAUS Alphanumeric Route M3.svg Frankston Freeway
Seaford, Melbourne
Location(s)
LGA(s)
Major suburbs / towns Ringwood, Wantirna, Scoresby, Rowville, Dandenong North, Keysborough, Carrum Downs, Seaford
Highway system

EastLink is a tolled section of the M3 freeway linking a large area through the eastern and south-eastern suburbs of Melbourne, Australia. [1]

Contents

EastLink is electronically tolled with no cash booths, using a system developed by SICE. The SICE Tolling System is similar to (and interoperable with) the e-TAG system used on the CityLink tollway. EastLink was opened to traffic on Sunday 29 June 2008 and in conjunction with the opening, a month-long toll-free period occurred before regular tolling commenced on 27 July 2008. [2]

The project was constructed by a joint venture of Australian construction companies Thiess Contractors and John Holland, [3] with tolling system contracted to SICE, and mechanical and electrical work contracted to United Group Infrastructure. [4] The final project cost was A$2.5 billion.

Signs are at the entrances and on the tollway direct to Ringwood, Dandenong, Frankston and Doncaster.

History

Construction of EastLink over Boronia Road in Wantirna EastLink Boronia Road.jpg
Construction of EastLink over Boronia Road in Wantirna
Eastlink in December 2009 Dandenong - panoramio.jpg
Eastlink in December 2009

The road was originally shown in the 1969 Melbourne Transportation Plan as the F35 Freeway.

The freeway has been a contentious issue, amid concerns over environmental damage and the possibility it would lead to a 'complete' metropolitan ring road. In October 1999, the incoming Bracks Government announced that the freeway (which Labor had not promised at the election) had been scrapped. Instead the government promised to investigate a preferred route for the Rowville railway line and extend tram route 75 to Knox, neither of which have eventuated. [5] However, in a "major policy about-face", the Bracks Government announced in August 2000 that it would seek federal funding for the freeway. [6] To obtain funding, the freeway would need to be classified as a road of "national importance", despite the fact that it did not form part of the national highway system. The "U-turn"' on the freeway was strongly criticised by opponents such as the Public Transport Users Association, because it would result in proposed public transport alternatives, such as the Rowville railway line, being scrapped. [7]

In 2001, University of Melbourne academic Paul Mees launched legal action in the Federal Court seeking an injunction, under section 475 of the Environment Protection and Biodiversity Conservation Act 1999, to prevent Transport Minister Peter Batchelor and the Roads Corporation (VicRoads) from "taking any further action relating to the construction of the Scoresby freeway or the Eastern Ring Road". He alleged that the freeway would threaten migratory birds, plant species and wetlands and that the freeway was part of a larger plan to build a metropolitan ring road to Greensborough. [8] In light of the court case, state government bureaucrats removed references to the metropolitan ring road from a draft Metropolitan Strategy. [9]

In 2003, the Southern and Eastern Integrated Transport Authority (SEITA) was established by the Victorian Government, to manage and oversee the project on behalf of the government. SEITA was responsible for managing the process of selecting a private sector bidder. [3]

In October 2004, SEITA awarded the contract for the design, construction, and operation of EastLink to ConnectEast, a company that was publicly listed on the ASX in November 2004. ConnectEast subsequently contracted Thiess John Holland, a group formed by the partnership of two major construction companies, to carry out the detailed design and construction of EastLink. [3]

ConnectEast, as owner of the road, is responsible for its day-to-day management until the concession deed expires in 2043. EastLink's construction began in March 2005, and the road opened on 29 June 2008.

The opening of the road on 29 June 2008 saw traffic on nearby Stud, Springvale and Blackburn Roads drop by 30% to 40%, [10] but traffic on the Eastern Freeway rose by 5 per cent at the Burke Road intersection, and by about 1–2 per cent at Hoddle Street in the city. [11] On average 270,868 cars, trucks and motorbikes travelled on the road every day until the tolling was introduced on 23 July. [12] In the first week after the introduction of tolls, the average number of daily trips fell to 133,722. This was in line with estimates of a 40 to 50 per cent decline, but is a third below prospectus forecasts. The average toll per trip was $3.10 – above the estimate of $2.91. [12]

In its first six months of operation, Eastlink made a loss of almost $93 million. [13] In 2010, the road had to be refinanced, with its traffic forecasts rewritten due to lower than expected traffic volumes. [14]

Naming history

Over the years the project was variously referred to as the Eastern Ring Road, Scoresby Freeway, Scoresby Bypass, and Mitcham-Frankston Freeway.

On 23 March 2005, with the beginning of construction on the project, then Premier Steve Bracks announced that the road would be called EastLink, at a ceremony in Rowville. [15] The new name was reportedly chosen because it was easier to say, apparently easier to remember, and would fit on street directories.

On 27 February 2008, it was announced that the EastLink / Monash Freeway interchange would be named the "Tom Wills Interchange", after the founder of Australian rules football Tom Wills. [16] On 24 March 2008, Roads Minister Tim Pallas announced that the twin tunnels would be named "Melba" and "Mullum Mullum", in the inbound and outbound direction respectively. [17]

Route

EastLink begins at the eastern end of the Eastern Freeway at Springvale Road in Nunawading, before tunnelling eastward towards Ringwood under the Mullum Mullum Creek area. It then travels 40 km south towards Frankston, passing through the suburbs of Wantirna, Wantirna South, Scoresby, Rowville, Mulgrave, Dandenong North, Noble Park, Keysborough, Dandenong South, Bangholme, and Carrum Downs, before ending at the northern end of the Frankston Freeway. [18] The majority of the freeway has three lanes running in each direction, while between Thompson Rd and Frankston Freeway, there are 2 lanes running in each direction. [19]

The standard travel time on EastLink in both directions, is 26 minutes, (12 minutes between Frankston Freeway / Peninsula Link and the Monash Freeway, 7 minutes between the Monash Freeway and the Burwood Highway and 7 minutes between the Burwood Highway and Springvale Road). Typical travel time is between 30 and 40 minutes.

EastLink does not regularly have peak period congestion like other urban metropolitan freeways in Melbourne. However, delays can be experienced following roadworks or they might be residual, following an incident. Occasionally, traffic congestion occurs between Thompsons Road and the junction with the other three freeways in Carrum Downs, where the freeway changes from three to two lanes. If the congestion builds, the travel time can reach 40 minutes or beyond.

Exits and interchanges

LGALocationkmmiDestinationsNotes
WhitehorseManningham boundary NunawadingDonvale boundary0.00.0AUS Alphanumeric Route M3.svg Eastern Freeway (M3) – City Northern terminus of tollway; continues west as Eastern Freeway
Australian state route 40.svg Springvale Road (State Route 40)  Donvale, Nunawading Single point urban interchange
Manningham Donvale 1.20.75Toll point 1
1.7–
3.3
1.1–
2.1
Melba Tunnel northbound / Mullum Mullum Tunnel southbound
Maroondah Ringwood 3.92.4Australian state route 62.svg Ringwood Bypass (State Route 62)  Ringwood, Lilydale Semi-directional T interchange; northbound exit uses Maroondah Highway exit and passes it
4.42.7Australian state route 34.svg Maroondah Highway (State Route 34)  Ringwood, Lilydale, Box Hill, Mitcham Modified SPUI; northbound exit left turn only - northbound-eastbound must proceed on ramp via Bypass
5.13.2Toll point 2
6.13.8Australian state route 32.svg Canterbury Road (State Route 32)  Montrose, Vermont
Knox Wantirna 6.94.3Toll point 3
7.64.7Australian state route 36.svg Boronia Road (State Route 36)  Boronia, Vermont
8.65.3Toll point 4
WantirnaWantirna South boundary9.35.8Australian state route 26.svg Burwood Highway (State Route 26)  Burwood, Ferntree Gully
Wantirna South10.26.3Toll point 5
11.16.9Australian state route 24.svg High Street Road (State Route 24)  Glen Waverley, Ferntree Gully
12.27.6Toll point 6
Scoresby 148.7Australian state route 22.svg Ferntree Gully Road (State Route 22)  Ferntree Gully, Oakleigh
15.19.4Toll point 7
15.39.5Dalmore Drive / Eastlink Outbound BP Service CentreSouthbound exit and entry only
Eastlink Inbound BP Service CentreNorthbound exit and entry only
Rowville 16.510.3Australian state route 18.svg Wellington Road (State Route 18)  Mulgrave, Rowville
17.310.7Toll point 8
Monash Mulgrave 18.111.2Australian state route 16.svg Police Road (State Route 16 west)  Springvale, Dandenong Southbound exit and northbound entrance only
Greater Dandenong Dandenong North 18.911.7AUS Alphanumeric Route M1.svgWestern Australia MR-SM-11.svg Monash Freeway (M1) – City, Warragul, Melbourne Airport Tom Wills Interchange; no northbound exit to M1 south-eastbound, no southbound entry from M1 north-westbound
19.312.0Australian state route 16.svg Police Road (State Route 16 west)  Springvale, Dandenong Northbound exit only, via Monash Freeway exit ramp
20.812.9Toll point 9
Dandenong NorthDandenongNoble ParkNoble Park North quadripoint 21.513.4Australian national route ALT1.svg Princes Highway (National Alt Route 1)  Dandenong, City
Keysborough 25.816.0Toll point 10
24.315.1Australian state route 10.svg Cheltenham Road (State Route 10)  Mentone, Dandenong Southbound exit and northbound entrance
25.315.7Australian state route 49.svg Dandenong Bypass (State Route 49 west, no shield east)  Keysborough, Dandenong South
25.816.0Toll point 11
26.516.5Australian state route 12.svg Greens Road (State Route 12)  Mordialloc, Narre Warren
Bangholme 31.319.4Toll point 12
FrankstonGreater Dandenong boundary Carrum DownsBangholme boundary33.120.6Australian state route 6.svg Thompson Road (State Route 6)  Carrum, Cranbourne
Frankston Carrum Downs 35.522.1Toll point 13
36.922.9AUS Alphanumeric Route M11.svg Mornington Peninsula Freeway (M11)  Baxter, Rosebud, Portsea Southbound exit to M11 south-eastbound, northbound entrance from M11 north-westbound
Seaford 37.723.4Rutherford Road  Frankston Southbound exit and northbound entrance only
AUS Alphanumeric Route M3.svg Frankston Freeway (M3)  Frankston Southern terminus: continues south as Frankston Freeway

Dandenong Bypass

A 4.8 km section of the Dingley Freeway called the Dandenong Bypass (also referred to as the Dandenong Southern Bypass during its construction) was built by ConnectEast and Thiess John Holland as part of the EastLink project. [20] The bypass opened on 9 December 2007. [21]

Tolling

Ringwood portal of the tunnels under the Mullum Mullum Valley Eastlink tunnels Ringwood portal.jpg
Ringwood portal of the tunnels under the Mullum Mullum Valley
Hillcrest Reserve and the Eastlink Melba Tunnel in January 2020 Hillcrest Reserve and the Eastlink Melba Tunnel.jpg
Hillcrest Reserve and the Eastlink Melba Tunnel in January 2020

EastLink is electronically tolled via a system commercially called Breeze, entirely provided by SICE, Spanish system integrator company with broad experience in the tolling market. This system is fully interoperable with all other tollways in Australia, including the Transurban e-TAG system used on CityLink. [22]

The system features a uniquely designed electronic vehicle tag, the "Breeze Tag", which is about half the size of the standard design of e-TAG. The Breeze system is provided by Spanish company SICE, [23] with the Road Side Equipment, including the Breeze Tags, provided by Swedish firm Kapsch TrafficCom AB, under the PREMID brand of DSRC products. [24]

Tolls on EastLink can be charged in three different ways:

If a driver travels on EastLink without taking any of the three actions above to pay for the toll(s) either prior to, or within three days after travel, an invoice for cost of the toll(s) plus an account processing fee will be sent to the registered vehicle's owner. If the toll invoice is not paid, an overdue notice (with an additional processing fee) is issued. If the invoice is still not paid, a fine is issued by Victoria Police. [28]

The concession period held by ConnectEast is due to end on 30 November 2043, [29] after which the ownership of the road will be transferred to the state.

Prices and discounts

Inside the Melba (westbound) tunnel Melba tunnel.jpg
Inside the Melba (westbound) tunnel

Multiple toll points are located along the EastLink, with each toll point charging a fixed fee. [30] The total toll incurred per trip is the smaller of the trip cap or the total price of toll points passed through. The exception is taxis which pay a fixed price for travel on any section south of Maroondah Highway, regardless of the distance travelled or number of toll points passed through.

The cheapest toll points are located between Maroondah Highway and High Street Road, with slightly more expensive toll points located in the longer sections near the south of the tollway, and the most expensive one within the tunnel section between Maroondah Highway / Ringwood Bypass and Springvale Road. Motorcycle prices are half of cars, while higher rates apply for larger vehicles. [31]

Discounts are also offered to car drivers. A 20 per cent discount applies to the cost of any car trip(s) taken on a Saturday or Sunday and also to one way trips between two consecutive interchanges (excluding the tunnels) on weekdays.

Toll prices as of 1 July 2023
Toll roadToll section or toll pointsMaximum toll price per tripToll increaseToll concessionaireExpiry of toll concession
CarsMotorcyclesLight Commercial VehiclesHeavy Commercial Vehicles
EastLink [32] Tunnel section$3.34 [lower-alpha 1] $1.67$5.36$8.88Annually on 1 July ConnectEast 2043 [33]
Each of the four toll points between Maroondah Highway and High Street Road$0.48 [lower-alpha 1] $0.24$0.78$1.29
Each of the six toll points between High Street Road and Greens Road$0.73 [lower-alpha 1] $0.36$1.17$1.94
Each of the two toll points between Greens Road and Mornington Peninsula Freeway$1.71 [lower-alpha 1] $0.85$2.72$4.51
Trip cap$7.29 [lower-alpha 1] $3.64$11.66$19.32
  1. 1 2 3 4 5 Prices shown for cars are weekday prices. Weekend and public holiday prices are 80% of weekday prices (weekend and public holiday trip cap is $5.83.

Traffic impact on surrounding roads

Whilst the construction of Eastlink alleviated congestion on Springvale Road, it has had the effect of funnelling the traffic onto other roads, particularly increasing traffic on the Eastern Freeway. Many local councils, organisation, community groups and individuals expressed concerns throughout the proposal and construction phases, over the alterations to traffic patterns and flows and how Eastlink would impact upon local roads in their respective areas. In 2009, the City of Manningham was able to conduct a traffic report which found that: [34]

Another study conducted by Banyule Council showed that, since EastLink opened in June 2008, 800 more trucks a day use main roads in Heidelberg and Rosanna.

In general, it appears as though Eastlink has funnelled large amounts of traffic onto the Eastern Freeway and has attracted an increase in commuters using arterial roads in local areas. Decreases appear to be on small stretches of local roads where Eastlink provides a quicker alternative.

Shared path

The EastLink Trail is a shared walking and cycle path that follows a similar north–south route to the EastLink project. Using it, cyclists and pedestrians are able to cycle or walk most of the distance of the road, along a 3-metre wide dedicated concrete path. Many major roads are crossed via under or over passes. Some roads, such as High Street Road (and until November 2009, Burwood Highway), require crossing the road at grade. [35]

In wet weather, two underpasses are not trafficable as they have been built on floodways. These are the Ferntree Gully Road underpass and the Wellington Road underpass. After a medium amount of rain the underpasses flood and trail users must cross over the major roads to continue along the path. This can prove dangerous and during peak traffic times, trail users are known to have waited up to 20 minutes to safely cross the roads when the underpasses have flooded.

The Eastlink trail stops in Dandenong and does not continue. Users may take the Dandenong Creek Trail from this point which will take them to Carrum, where they will be able to join the Peninsula Link trail to Frankston and Mornington.

For those using the trail, substantial deviations from EastLink must be taken into account in travel times as the shared path does not follow the freeway in many cases as existing trails were joined up to the trails specifically built during the construction of the road. This has led to some very twisty sections of trail and in some cases, detours of over 3 km from the EastLink.

EastLink Melbourne from Heatherton Road Looking North.jpg
A panoramic view of EastLink looking north from the Heatherton Road bridge.

Accidents

On 18 February 2010, at 3.15 pm, a semi-trailer lost control on the north-bound side of the tollway, 300m from the Wellington Rd exit. The truck crossed the road and crashed through the median safety barrier, before crashing into a large pylon holding up a road sign gantry. The truck exploded into flames and the driver was killed. The tollway was closed in both directions, the first time since the road opened, between the Monash Freeway and Ferntree Gully Road. It remained closed until the early hours of the following morning so police could conduct an investigation and ConnectEast could carry out repairs to make the road safe to reopen. The police report is yet to be finalised.[ citation needed ][ needs update ]

Controversies

Maroondah Highway bridge, Ringwood looking towards the railway bridge Eastlink first day open.jpg
Maroondah Highway bridge, Ringwood looking towards the railway bridge
EastLink looking south from the Koomba Road footbridge before opening. EastLink looking south from Koomba Road bridge.jpg
EastLink looking south from the Koomba Road footbridge before opening.
The EastLink Operations Centre in Ringwood during construction. EastLink Operations Centre.jpg
The EastLink Operations Centre in Ringwood during construction.
Night-shot of overpass spanning Eastlink, near the Burwood Rd exit. Eastlink overpass.JPG
Night-shot of overpass spanning Eastlink, near the Burwood Rd exit.

Environmental issues

Constructing the EastLink bridge over Dandenong Creek, in Ringwood/Wantirna EastLink Bridge over Dandenong Creek.jpg
Constructing the EastLink bridge over Dandenong Creek, in Ringwood/Wantirna

Many environmental groups in Melbourne's east and south-east objected to the project, due to a number of factors, including vehicle emissions and disruption of habitat (in places such as the Mullum Mullum Valley and Dandenong Valley Wetlands). However, the road was the subject of an extensive Environmental Effects Statement (June 1998), which was followed by an extensive public hearing process in April 1999 before the final Government decision to proceed. The statement predicted an 18.5per cent increase in carbon dioxide, impacts on groundwater and wetlands, high impacts on areas of conservation value and the potential to affect 38 species of rare or threatened fauna and flora if the freeway was built. [8]

According to EastLink's builders, the road will relieve traffic congestion throughout Melbourne's eastern and south-eastern suburbs, resulting in more efficient traffic flow, therefore reducing fuel consumption and exhaust output. [37] However, like all such road projects, the phenomenon of induced demand will work against the realisation of those benefits. [38]

During the planning phase (then a VicRoads project), a large debate surrounding damage to the Mullum Mullum Valley occurred. A number of options for the path of the road through the valley were considered. The option chosen – for two 1.6 km tunnels – was the second-to-most expensive, and the second-to-most environmentally friendly. [39] Other options considered in planning included a surface road for the entire length, much shorter tunnels, and slightly longer tunnels.

However, despite the attention on tunnelling beneath the Mullum Mullum Gorge, the Ringwood Interchange is entirely above-ground and has resulted in relocation of the creek through this area.

See also

Related Research Articles

<span class="mw-page-title-main">Carrum Downs, Victoria</span> Suburb of Melbourne, Victoria, Australia

Carrum Downs is a suburb in Melbourne, Victoria, Australia, 36 km south-east of Melbourne's Central Business District, located within the City of Frankston local government area. Carrum Downs recorded a population of 21,976 at the 2021 census.

<span class="mw-page-title-main">Doncaster East, Victoria</span> Suburb of Melbourne, Victoria, Australia

Doncaster East is a suburb of Melbourne, Victoria, Australia, 20 km east of Melbourne's Central Business District, located within the City of Manningham local government area. Doncaster East recorded a population of 30,926 at the 2021 census.

<span class="mw-page-title-main">Monash Freeway</span> Freeway in Victoria, Australia

The Monash Freeway is a major urban freeway in Victoria, Australia, linking Melbourne's CBD to its south-eastern suburbs and beyond to the Gippsland region. It carries up to 180,000 vehicles per day and is one of Australia's busiest freeways. The entire stretch of the Monash Freeway bears the designation M1.

<span class="mw-page-title-main">Eastern Freeway (Melbourne)</span>

The Eastern Freeway is an urban freeway in eastern Melbourne, the state capital of Victoria, Australia. It is one of the most important freeways in terms of commuting to the city, connecting Alexandra Parade and Hoddle Street in the inner suburbs, with EastLink tollway farther east. It consists of between three and six lanes in each direction, also an inbound transit lane reserved for vehicles with two or more occupants during peak hours.

<span class="mw-page-title-main">Mornington Peninsula Freeway</span> Freeway in south-eastern Melbourne, Victoria, Australia

The Mornington Peninsula Freeway is a freeway in Melbourne, Victoria, Australia, that provides a link from south-eastern suburban Melbourne to the Mornington Peninsula. Whilst the entire freeway from Dingley Village to Rosebud is declared by VicRoads as the Mornington Peninsula Freeway, the section between EastLink in Carrum Downs and Moorooduc Highway in Moorooduc is locally and commonly known as Peninsula Link. The entire freeway corridor bears the designation M11.

<span class="mw-page-title-main">Frankston Freeway</span> Freeway in Victoria

Frankston Freeway is a short freeway in southern Melbourne initially designed as a bypass of central Frankston and later incorporated a freeway-style upgrade to Wells Road in the 1970s, now acting as a link from suburban Melbourne to Frankston's eastern suburbs.

<span class="mw-page-title-main">Dandenong Valley Highway</span> Highway in Victoria

The Dandenong Valley Highway is an urban highway stretching almost 40 kilometres from Bayswater in Melbourne's eastern suburbs to Frankston in the south. This name covers many consecutive streets and is not widely known to most drivers, as the entire allocation is still best known as by the names of its constituent parts: Stud Road, Foster Street, Dandenong-Frankston Road, Dandenong Road West and Fletcher Road. This article will deal with the entire length of the corridor for sake of completion, as well to avoid confusion between declarations.

<span class="mw-page-title-main">Mullum Mullum Creek</span> Creek in Victoria, Australia

Mullum Mullum Creek is a creek in the outer eastern suburbs of Melbourne, Victoria, Australia. It is the main watercourse of the Mullum Mullum Valley, a tributary of the Yarra River and Yarra Valley. For tens of thousands of years it was used as a food and tool source sustainably by the Wurundjeri people, Indigenous Australians of the Kulin nation, who spoke variations of the Woiwurrung language group.

ConnectEast is an Australian company responsible for the finance, design, construction and operation of the EastLink toll road in Melbourne.

<span class="mw-page-title-main">Dandenong Creek Trail</span> Suburban trail in Melbourne, Australia

The Dandenong Creek Trail is a shared use path for cyclists and pedestrians, which follows Dandenong Creek through the outer eastern and south-eastern suburbs of Melbourne, Victoria, Australia.

<span class="mw-page-title-main">Dingley Arterial Project</span> Road in Melbourne, Australia

The Dingley Arterial Road Project is a partially completed arterial standard road which runs east to west through the southern suburbs of Melbourne, Australia.

The Dandenong Bypass is a highway in the state of Victoria, Australia that runs along the Dingley Freeway reservation from Springvale Road in Keysborough to the South Gippsland Highway in Dandenong South.

<span class="mw-page-title-main">Blind Creek Trail</span>

The Blind Creek Trail, in the outer eastern suburbs of Melbourne, in the Australian state of Victoria, is a shared-use path for cyclists and pedestrians, which follows the Blind Creek from the Dandenong Creek Trail in Wantirna South to the Ringwood - Belgrave Rail Trail in Boronia.

<span class="mw-page-title-main">Ringwood to Belgrave Rail Trail</span> Rail trail in Victoria, Australia

The Ringwood - Belgrave Rail Trail is a shared use path for cyclists and pedestrians, which follows the Belgrave railway line from the Mullum Mullum Creek Trail in Ringwood to Belgrave railway station in Belgrave, in the outer eastern suburbs of Melbourne, Victoria, Australia.

The Ringwood Bypass is a short stretch of road extending from EastLink to Maroondah Highway in Melbourne, Australia. It allows the Maroondah Highway to bypass Eastland Shopping Centre, in the eastern Melbourne suburb of Ringwood.

<span class="mw-page-title-main">1969 Melbourne Transportation Plan</span>

The 1969 Melbourne Transportation Plan was a road and rail transport plan for Melbourne, the state capital of Victoria, Australia, instituted by Henry Bolte's state government. Most prominently, the plan recommended the provision of an extensive freeway network, much of which has since been built.

<span class="mw-page-title-main">North East Link</span> Tollway under construction in Melbourne

The North East Link is an under construction 10–kilometre tolled highway scheme in Melbourne, Australia. It will connect the Metropolitan Ring Road at Greensborough with the Eastern Freeway at Bulleen, which will be upgraded from Hoddle Street to Springvale Road at Nunawading.

<span class="mw-page-title-main">EastLink Trail</span> Suburban trail in Melbourne, Australia

The EastLink Trail is a shared use path for cyclists and pedestrians in the outer eastern/southeastern suburbs of Melbourne, Victoria, Australia. The trail gets its name from the north-south EastLink tollway, along which it follows for most of its length from Ringwood to Dandenong, until it joins the Dandenong Creek Trail near the Dandenong Bypass bridge at the tri-suburban junction between Dandenong, Dandenong South and Keysborough.

<span class="mw-page-title-main">Box Hill to Ringwood Rail Trail</span>

The Box Hill to Ringwood Rail Trail is a shared use path that runs alongside the Belgrave and Lilydale Lines in the east of Melbourne, Australia. The route serves a total of seven railway stations. The bike path is incomplete, as the section between Blackburn and Laburnum is yet to be constructed.

References

  1. 1 2 3 "Who's involved?". Southern and Eastern Integrated Transport Authority. Archived from the original on 1 June 2008. Retrieved 26 June 2008.
  2. Woodberry, Trent (12 December 2006). "EastLink: – Commencement of mechanical and electrical work by United Group Ltd" (PDF). Thiess John Holland. Archived from the original (PDF) on 25 July 2008. Retrieved 26 June 2008.
  3. Das, Sushi (8 August 2000). "Scoresby Freeway Back on Agenda". The Age. p. 3.
  4. Das, Sushi (21 August 2000). "Anger at U-turn on Scoresby Freeway". The Age. p. 3.
  5. 1 2 Heasley, Andrew (27 October 2001). "Scoresby Freeway Faces Hurdle". The Age. p. 13.
  6. Heasley, Andrew (31 October 2002). "Ring road plan altered before case". The Age. p. 6.
  7. Milesi, Julia (30 June 2008). "No delays as EastLink tollway cuts traffic". The Age. Retrieved 17 August 2008.
  8. Gardiner, Ashley (1 July 2008). "Traffic on surrounding roads plummets after EastLink opens". Herald Sun. news.com.au. Archived from the original on 3 August 2008. Retrieved 17 August 2008.
  9. 1 2 Beveridge, John (8 August 2008). "Road fees take a toll". Herald Sun. news.com.au. Retrieved 17 August 2008.
  10. Silkstone, Dan (24 March 2005). "Naming and blaming launches tollway". The Age. p. 10.
  11. EastLink interchange honours one of football's founders Archived 5 September 2009 at the Wayback Machine SEITA. 27 February 2008. Retrieved 26 March 2008.
  12. Pilcher, Georgie (24 March 2008). "East Link Twin Tunnels named as Melba and Mullum Mullum". Herald Sun. Australian Associated Press.
  13. "Dandenong Bypass". Southern and Eastern Integrated Transport Authority. Archived from the original on 19 July 2008. Retrieved 26 June 2008.
  14. EastLink tollway to open six months early Herald Sun 10 December 2007. Retrieved 12 December 2007.
  15. "Breeze – Products". ConnectEast. Retrieved 26 June 2008.
  16. "Kapsch awarded new prestigious contract in Australia". Kapsch TrafficCom AB. 2 September 2005. Archived from the original (PDF) on 7 July 2007. Retrieved 26 June 2008.
  17. "Breeze – Tag account". ConnectEast. Retrieved 26 June 2008.
  18. "Breeze – Non-tag account". ConnectEast. Retrieved 26 June 2008.
  19. "Breeze – EastLink trip pass". ConnectEast. Retrieved 26 June 2008.
  20. "Breeze – Toll invoice". ConnectEast. Retrieved 26 June 2008.
  21. "Department of Transport Annual Report 2020-21" (PDF). Department of Transport (Victoria) . Melbourne: Victorian Government. October 2020. p. 103.
  22. "Melbourne toll calculator". Linkt. Retrieved 2 December 2021.
  23. "EastLink Tolls valid 1 Jul 2023 until 30 Jun 2024" (PDF). EastLink. Retrieved 29 February 2024.
  24. "Advert - General Counsel & Company Secretary" (PDF). EastLink. Retrieved 6 August 2021.
  25. City of Manningham, traffic report on the effects, alterations and impacts of Eastlink to surrounding and local roads in the City of Manningham, 2009.
  26. "Chaos after EastLink bungle". Herald Sun. 28 August 2006. pp. Internet Article.
  27. Gardiner, John (March 2006). "In the Headlights". EastLink News. ConnectEast. p. 2. Vehicles travelling at reasonably consistent speeds use less fuel ... emissions are all reduced by better and more consistent speeds.
  28. Jaffe, Eric (11 November 2015). "California's DOT Admits That More Roads Mean More Traffic". Bloomberg.com. Retrieved 22 January 2018.
  29. Costa, Gabrielle (14 October 2000). "Government compromises on freeway". The Age. p. 4.